Commercial Construction
Completed
Surrey Commercial Cold-Chain Logistics Complex
Mashonaland East
Client
Private commercial client
Contract Type
Lump Sum Turnkey
Timeline
2023 - 2024
Industry
Commercial
Timeline
2023 - 2024
The Challenge
Stringent international food safety standards (HACCP) required crack-free, dustless concrete floors with zero tolerance for standing water, coupled with an aggressive 9-month critical-path program prior to festive season retail launch.
Engineering Approach
Deployed laser-guided floor screeding technology and dry-shake metallic surface hardeners. Steel portal structures fabricated off-site under strict QA/QC shop welding protocols and erected with 50-ton mobile cranes during sequenced work windows.
Scope Breakdown
Structural steel portal frames, FM2-specification laser-screed jointless concrete industrial floor slabs, food-grade insulated composite panel envelope, dock levellers, and integrated retail facilities.
Outcomes & Impact
- Handed over 2 weeks ahead of scheduled retail launch.
- Achieved FM2 floor flat standard for high-reach narrow-aisle forklift operations.
- Refrigeration thermal envelope certified with zero thermal bridging.
Operational Gallery